GREEN                                                

  AND

       CLEAN

                POWER

French River Land Company's Website!

 

French River Land Company's Home Page!

Poetry of Power

FRL History

Hydrolec Disassembly

Hydrolec Rebuild

Key Personnel

Machine Shop

News Page

Previous Pictures

Previous Pictures Two

Previous Pictures Three

Previous Pictures Four

Bill Munch

Projects

Rebuilding 120" Niles Boring Mill

For Sale

HYDROELECTRIC SITES:

Alternatives Hydro

Anasagunticook Lake Dam Replacement-    C.Fay & W.Fay

Appleton HEP-Jim Lichoulas

Appleton Wisconsin Anniversary

Badger Pond Dam Removal

Senor Bonifettis' sites in Chile

Chittendon Falls

Claytor Dam

Collins Bascule Dam

ESAC WORKS      July 1985

Fiske Mill

1852 Fourneyron

Golden Pond Hydro

Harry Terbush Sites

Hunts Pond

Indian River Rebuild

Kaplans

Jaffery Fire Protection

Konkapot Creek

Lake May Pelton Wheel Removal

Livermore Falls

Martinsville Hydro

OSV

Pepperell

Shaker Mill Dam

Silk Knitters- Ron MacLeod

South Village Dam

Sparhawk Mills

Tannery Pond

Tannery Rebuild

Turners Falls Generator Rewind

Valatie Falls

Valley Paper

Wynoochee Hydro

USEFUL ENGINEERING:

Admitting Air to Turbine Runners Improves Efficiency, S. Logan Kerr

Air Admission to Hydro Runners, David Cox, USCOE, Kerr Dam

Archimedian Screw Pump Handbook- Gerhard Nagel

A Self-Adjusting Spring Bed Bearing- Henry G. Reist ASME 1646

The Banki Water Turbine Mockmoore and Merryfield

Barrel Stave Bearing Repair

Bearing Currents: Their Origin and Prevention C. T. Pearce

Bishops Method- STABGM Program

Blade Design Kovalev

Blade Pitting- Boving LTD 1930

Cavitation- Accelerated Research, Allis Chalmers Research

Cavitation & Vibration of a Draft Tube

Cavitation- Prevention & Reduction, Allis Chalmers Research

Causes & Effects of Cavitation in Hydraulic Turbines

Chain Turbine by: Nguyen Minh Duy

Chain Turbine Mechanics- Discussions with Duy

Characteristics of Modern Hydraulic Turbines-Chester Larner

Comparative Tests On Experimental Draft Tubes- C M Allen & I A Winter  1923

Design of an Overshot Waterwheel

(by Carl Weidner)

Design of Pelton Buckets

Design of Small Water Turbines for Farm and Small Communities

Design of the runner of a Kaplan turbine for small hydroelectric power plants: Timo Flaspöhler

Draft Tube Design

Draft Tubes of Hydro-Electric Stations by M. F. Gubin

Draft Tube Tests

Ejection into Tailraces of Hydropower Plants: S. M. Slisskii

Erection & Alignment of Vertical Waterwheel Generator Units-R.O. Standing

Evolution of Hydraulic Prime Movers-Byron McCoy

Fall Increaser- Henry Ford

Fall Increaser Herschel Venturi Tube

Fall Increaser Moody Ejector Turbine

Fall Increaser Hydraulic Jump Apron

Flashboard Pins

Gatecase Design- Kovalev

Generator Shaft Design Calculation- Olav Hodtvedt

Governor Theory for the Plant Operator

Graphics of Water Wheels- William Fox

Hydraulic Motors- M. Bresse & F. A. Mahan 1869

Hydraulic Power Transmission by Compressed Air

Hydraulic Rams their Principals and Construction by J. Wright Clarke

Hydraulic Turbine and Governor Field Erection Information

Hydraulic Turbines- Robert Long Daugherty

Hydraulic Turbines by Arnold Pfau

Hydraulic Turbines Gelpke & Van Cleve

Hydrokinetic Energy in Massachusetts, William D. B. Fay

Hydrostatic Beam Analysis

HYDROTURBINES DESIGN AND CONSTRUCTION N. N. KOVALEV

Impulse Turbines  by Ely Hutchinson

Interference fitting a large runner shaft

Kaplan Blade Design NACA Air Foil- Report No. 460

Kaplan Blade Design NACA Air Foil- Report No. 628

Kaplan Design- Kovalev

Kaplan Design Marko Kogovsek.xls

A Laboratory Study to Improve the Efficiency of Crossflow Turbines- N. Aziz & V. Desai

Loading Vertical Thrust Bearings R. C. Johnson

Low Head Hydroplants, Emil Mosonyi

Meggering Generators

Meggering      Earth Resistance

Motors as Generators for Microhydro, Nigel Smith

Miroslav Nechleba

Natick Dam Powerhouse Calcs

Operation & Maintenance of Hydro-Generators

Out Gassing of Cross Flow Turbines

Parallel Operation of Turbines Analysis

Pelton Design- Daugherty

Pole Key Extraction

Pouring a babbitt bearing

Powerhouse Design- Miniwatt Hydro

Powerhouse Design- Natick Dam

Power Plant Inspection

Rake-Leonard

Rake-Newport News

Rack Design-Chicopee-Olav Hotvedt

Rack Design- PHI- Bill Fay

Rack Design-PHI-Brian French

Rack Design-PHI-Ken Smith

Rack Design-ASCE

Rack Design- Hydraulic Institue of Munich

Rack Design-Flow Induced Vibrations

Rigging a large generator

Selecting Hydraulic Reaction Turbines BUREC

Shafts- Kovalev

Shaft Couplings

Snows Improved Water Wheel Governor

Standard for Hydraulic Turbine and Generator Shaft Couplings and Shaft Runout Tolerances

Stoplog Design Calculation

Stoplog Structure Design Calculation

Stress Analysis of Hydraulic Turbine Parts, BUREC- F.O. Ruud

Some Fluid Flow Characteristics of a Cross Flow Type Hydraulic Turbine- Durgin & Fay

Technology of Heavy Electric Machine Building HydroGenerators

Tenth Census of the US, 1880, Water Power of the US, Part I- Professor Trowbridge

Tenth Census of the US, 1880, Water Power of the US, Part II- Professor Trowbridge

Tests on a Kaplan Hydraulic Turbine

Tests Of A Rife Ram

Theoretical Conditions Related to an Open Channel Flow Linear Turbine- Ishida & Service

Theory of Turbines- De Volson Wood

Tidal Energy for Hydroelectric Power Plants by L. B. Bernshtein

Treatise relative to the Testing of Water-Wheels and Machinery, James Emerson 1879

Trash Rack Differential Equations 2L/3

Trashrack Differential Equations General Solution f(x)

Turbine Water-Wheel Tests- Robert Horton

Turgo, A High Speed Impulse Turbine- Paul Wilson

Vortices at Intakes

Water Hammer and Surge Tanks G. V. Aronovich

Water Hammer-Lorenzo Allievi-Text

Water Hammer-Lorenzo Allievi-Figures

Water Hammer-ASME Symposium 1933

Water Hammer _ Norman Gibson

Water Hammer-E.B.Strowger

Waterpower Engineering-Daniel Webster Mead

Water Turbines Contributions to Their Study, Computation and Design-S.J. Zowski

Water Wheel Design- Ken Smith

Weights

WHAMO

White Hydraucone Regainer

Wooden Penstocks

TRADE CATALOUGES:

ASEA- Bearings for Large Vertical Hydro-Electric Machines

Bradway Turbine  (progressive gate)

C.P.Bradway Turbine

Brook Waterwheel

Charmilles Turbines

Christiana Machine (register gate)

Dayton Globe

Electric Machinery Company (EM)

English Pelton

ESAC

Essex Turbines

GE WW Vert Gen

GE Springbed Brg

General Electric- Standard Specifications for Hydro Thrust Bearings and Runners

General Electric-Thrust Bearings as used in Large General Electric Hydraulic Turbine-driven Generators- GEA 2251E

GEH 527C

Gilkes Turbines

GilkesWaterpower

Head Gate Hoists- S. Morgan Smith

Holyoke Hercules

Hunt Cat 29 A&B

Hunt cylinder

J & W Jolly       (cylinder gate)

Kingsbury  Brg

Leffel Bulletin 38

Leffel Bulletin 54

Leffel Hoppes Unit

Leffel Laboratory Unit

Leffel Miscellaneous

Kingsbury Catalog C-1

Lombard Direct-Connected Oil Pressure Governors Bulletin N0. 113 October 1st, 1912

Lombard Governor

Lombard Governor Company Type T Instruction Book

Lombard Governors for Waterwheels and Steam Engines-1902

Lombard Water Wheel Governors Catalouge 26

Michell Bearings

Nohab- Water Turbines

Pelton Wheel (1909)

Pelton Wheel (1925)

Rife Hydraulic Engine

Ridgway Perfection Water-Wheel

Rodney Hunt

Samson PamK

Smith Bulletin 110

Smith Power Tables

Smith Kaplan

Smith Power

Smith Pelton

Smith Develop

Smith Turbines: Bulletin 105

Swain Turbine

Trump Hydraulic Turbines

Trump Turbines

Tyler Turbine

Vertical Shaft Water Wheel Driven Generators- General Electric

Wellman Seaver Morgan

Westinghouse Small Vertical Waterwheel-Driven A-C Generators, July 1944

Westinghouse WW Generators

Woodward Governor

 

Links:

Swiftriverhydro.com

damengineers.com

Smith Alternative Energy:

www.smithtest.com

 

 

Small Turbine Manufacturers Websites:

www.waterturbine.com

www.varspeedhydro.com

www.hydropower.nu

www.ossberger.de

www.gilkes.com/

 

 

Previous Pictures Three Web Page

I posted too many photographs on the website. It was becoming very slow to load. I moved some of the previously posted photographs here.

 

Celesty and Will getting ready to dive on the forebay at Woronoco HEP. Sand had built up in front of the west rack and the trash rake would not descend to the sill. They cleaned out the sand.

Removing the Rodney Hunt turbines at Livermore Falls, N.H. Bill Fay is using thermite bars to burn the 3 inch thick cast iron head covers at Livermore Falls. Here the cold of outer space (liquid oxygen at minus 297 deg F) is feeding the fires of hell (OxyAcetylene burns steel at 2500 deg F, the surface temperature of the sun is 16,000 deg F. The tip of the thermite bar runs 8,000 deg F). The thermite bars are consumed like a punk stick. As they burn down the 8,000 deg F gets very close to your hands!! Once they are ignited, we could carve our initials in solid granite. (Livermore Falls<<click here for Livermore Falls)

 

 

I had been searching for a 60 inch Bullard for several years. I could afford neither the $60,000 price tag, that they were going for, nor the $10,000 trucking charge. Finally I found this one, on e-bay, two towns over from the shop for $3500 that included the flag and digital read out!!! Here Will, Celesty and Ronnie have jacked it up and placed it onto caterpillar machinery rollers in order to ship it back to the shop. We were looking for a service manual. The folks who are supplying parts for Bullards told us to look on the cross slide for a 5 digit serial number that would help them select what manual to send to us. I looked and found only a three digit number. We told the number to the factory rep. He called back and told us our Bullard had left the factory in August of 1902!!! It was the oldest Bullard that he new of that was still being used in a commercial operation. I was very pleased to get it. Will did put on his steel toed boots after this photo was taken.

April 11th, 2009, added scanned textbook, Hydraulic Motors by M. Bresse as translated by F. A. Mahan, July 1869. Also added links to Part I and Part II of the 1880 US Census, Water Powers of the United States. Got up at 5:00 AM cleaned both sides of River Road of all trash from bridge to abandoned house. Got Collin's trash rake and swept beer bottles and trash from sun turtle's little pond.

April 2nd, 2009, added scanned textbook, Hydraulic Turbines by Victor Gelpke and A. H. Van Cleve

March 29th, 2009, added scanned text book, Theory of Turbines by De Volson Wood, Graphics of Water Wheels by William Fox and Standard for Hydraulic Turbine and Generator Shaft Couplings and Shaft Runout Tolerances.

March 23rd, 2009, added Characteristics of Modern Turbines- Chester Larner.

Celesty in action!!!! She is sitting on the Woronoco No. 2 pressure casing. Note the operator for the 72 inch butterfly valve over Mike's head. The crew is grouting the space between the old pressure case and the new steel plate liner. The waste paper basket is welded to a two inch pipe that is inserted between the two layers. See the second bucket located behind Celeste. We mixed the grout, emptied it into the buckets and vibrated it into the cavity.

Celesty in action!!!! She is at the bottom of the Chinese gate case at Brockway Mills. She is moving one of the 75 ton porta-power cylinders. You can see the remains of the Chinese volute case, that needed to be cut out, in order to install the 500 KW, Ossberger Turbine in place. Chris gave me the Dong Fang for cash and a promise to assist him with the concrete removal. The only place to insert the rectangular draft tube was to hammer out a 10 foot wide by 12 foot long by 15 foot deep hole in front of the volute case and breaking out into the roof of the elbow draft tube. We used 30 pound rivet busters to remove the yardage. It took 6 weeks of back breaking work. This plant is currently for sale. Chris has purchased property in Montseratt. He wants to drill obliquely towards the volcano and install several megawatts of vulcan-thermal, steam cycle power!! This is a beautiful plant and has been running superbly!!! He is asking $ 850,000 for the plant. I think it is a steal. If you have a serious interest, please call Chris at: 1-603-499-2350.

 

Celesty is inspecting the No. One turbine runner for damage at Pepperell Hydro. Note the chunk of missing runner blade she has discovered. She is holding her hand over the missing piece.

Celesty and Will in the ruins of Appleton Mills in Lowell, MA. Will is sitting on the endbell of the horizontal pressure case. Celesty is straddling one of the cylinder gate operating shafts. Please see the following "You Tube Video" of this site when it was restored in the 1980s by Dave and Luke Wright.

http://www.youtube.com/watch?v=efZfa8w7VNg <<< please click

March 18th, 2009, Added Operation and Maintenance of Hydro-Generators

March 11th, 2009, added brochure, Craig Ridgway, "Perfection" Water-Wheel and Shaft Couplings for Hydroelectric Units

March 10th, 2009, added brochure, Headgates by S. Morgan Smith Company

Here, I am using thermite bars to burn the salient pole rotor off of the Westinghouse shaft. We needed the shaft to make our hybrid WestFang Generator. The rotor had sat outside in the weather for so many years, that we were afraid of bending the shaft, if we pressed it out of the flywheel bore. Ronnie Johnson has just lit up the end of the bar with the 30 inch wrecking torch. Once the bar starts to sputter, you crank open the ball valve, on the collet holder and all hell breaks lose!! It never ceases to amaze me how destructive a thermite reaction can be. Kids don't do this at home!!

Celesty, Ronnie Johnson and Chris Krueger rigging the Brockway Mills Rotor in anticipation of lowering it into the powerhouse hatch. Look at the size of the crane block compared to Chris' head!!

Here, I am installing a 15,000 volt air break switch. I had to extend the crane boom, with two I-beams, to get the lift. See the heavy clamps I fabricated to hold the beam to the end of the boom. Note the real end of the boom ends at the boom sheave. I first had to extend the 40 foot ladder, climb to the top and rope it down. I then lifted up the two heavy channel irons and bolted them and the braces onto the pole. Next I lifted up the individual switches. I had to haul the welding cable up the ladder. That's me straddling the I-beams while I weld the outboard switch to the support channels. The commuters coming down Route 202, from the center of town, thought I was floating in air!

 

Bad picture of me welding on top of the 40 foot pole. Note the guard rails up on Route 202 in the background.

Here's my Celesty operating the cherry picker at one of our sites. She has been operating the crane for years. I get a chuckle out of seeing her bossing around 30 and 40 year old guys, telling them not to get under the boom or the load! The next photo is looking down the 45 degree tarred slope that constitutes our driveway!!! We are pulling the number one runner out of Woronoco to rehabilitate at our shop.

Here, Celesty is pushing the Brockway Mills synchronous generator stator into position. I am in the back corner operating two 5 ton chain cum-a-longs in series to take up the slack. The stator is hanging off the crane cable . The top of the boom is almost 200 feet above her and the cable is dropped down through three stories, of a concrete reinforced powerhouse.

Here is a photograph of the Brockway Mills Powerhouse, with the crane in place, to lower the new generator into the roof hatch. This is where the word gorgeous comes from!!!

 

Davis starts his surgical incision. Note the small pressure case to the right. The Clark's (of Clark's Trading Post Fame) 15 years previously removed a smaller turbine by drilling a million holes in the little cover. They than smashed the cover with large sledge hammers. The result was the same but Davis and I preferred the thermite bars.

+

Davis Hobbs dancing with the devil!! The heat was so intense that with an ambient temperature of over 100 degF we could only do two bars each. When we stopped we started shivering uncontrollably because the 100 degF day was so cold!!! See the Livermore Falls sidebar.

 

Celesty is slowly pulling the double runners up the hill. Left to right are Davis Hobbs, Ken Smith (aka: Mr. ESAC), me, crazy Chris Krueger and the best employee in the world, Mike Desrouche. We white blasted the runner, magnefluxed it for cracks, turned the bearing journals and coated the runners with Belzona's Super Glide. When it was finished, I did not want to go through this scene again. I rented a truck from Home Depot, loaded the runner on the back with the orange crane, drove down the Mass Pike to the site, and slowly (with some trepidation!!) backed down the hillside. I off loaded the runners with the chainfall located inside the powerhouse door.

Kenny is an excellent rigger. He was a merchant marine engineer and graduated from the Massachusetts Maritime Academy. Whenever I thought we were doing a difficult pick, I remembered Kenny telling me about picking a 10,000 pound cylinder head, off a large marine engine, during a storm!!! Instead of worrying about just gravity, he needed to secure the x-y plane against pitching and yawing of the ship, with no external reference, of where the waves were going to hit. Here, he is removing the dollies from the runners so we can lift it onto the crane.

One set of freshly rehabbed runners, about to go down the Mass Pike, to be backed down to the Woronoco Powerhouse. I was really hoping the brakes would hold and they did!!!We do nice work!!!

 

Out with the bad!!! One very corroded and damaged Leffel, 54 inch, "J" runner. Mike Desrouche, Ronnie Johnson and Marshall Smith riggers.

 

Back in with the good!! $ 130,000 later, one new, replacement American Hydro runner!! Marshall Smith, Dave Hobbs, Mr. ESAC and Mike Desrouche off loading the new runner.

March 8th, 2009, added Christiana, Jolly, Trump and 1902 Lombard Catalouges.

March 5th 2009, added link a link to "Treatise Relative to the Testing of Water-Wheels and Machinery, with Various Other Matters Pertaining to Hydraulics" James Emerson, Holyoke Testing Flume, 1878.

March 3rd 2009, added three Lombard Catalouges, four articles on cavitation and links to the classic textbooks, Waterpower Engineering by Dan Mead and Hydraulic Turbines by Daugherty.

Celesty and I are lowering the Leffel, 39 Inch, B-2 runner into the No. 2 pressure flume. The new main shaft was created by "The Wizard",  on our 28 foot long, Poreba, roll, lathe.  Celesty and Mike had just used the 3000 ft-lb, hydraulic torque wrench to tighten the 1/2 coupling onto the top of the runner. We are standing on top of the Westinghouse generator flange that I carved from the carcass of the number two generator with the thermite bars.

 

Can you imagine inventing a turbine, drawing it up, making the patterns, casting the iron parts, machining the pieces, assembling the machine and shipping it off to the famous Holyoke Turbine Testing Flume for efficiency tests. Now, imagine paying the famous Mr. James Emerson, for those tests and having this letter, not only sent back to you, but also published in an engineering textbook!! Mr. Emerson really needed a modern course in client relations! This was in the famous, first, edition, that was banned by the Roman Catholic Church, the only engineering textbook ever banned!!! This was not in the later editions of the book, "Treatise Relative To The Testing of Water-Wheels and Machinery, Also of Inventions, Studies and Experiments with Suggestions from a Life's Experience", James Emerson, Williamsett, MA. 1894. It was the latter part of the title and of the book that got Mr. Emerson in trouble with the Church.

 

Collins blew a 13,800 volt fuse yesterday. The crew opened the air break switch and killed the line. After inspecting the blown line, we found this burnt bushing. Notice the hairline crack in the porcelain. Water got in the crack and the high voltage tracked down the water to ground. Note the burned metal in the eye. No one saw it happen, but it must have been a spectacular explosion.

 

 

Celesty has just helped finish replacing the Ropac mechanical seal at the Collins site. The seal was in the No.2 ESAC unit. What other turbine mechanic cannot work without her ear rings!

Will and Celeste reassembling the GE thrust bearing at Turners Falls. They have installed the bearing and thermocouples and are just sliding on the cooling fan. The next morning we all left for three weeks in the Yucatan Peninsula.

Will cutting the 30 inch main support beam for the new stoplog structure at Woronoco Hydro. Here he is 11 years old and this is an enormous I-beam!

Celesty rigging out the back roller shaft at Consolidated Edison's, Gardiners Falls Station. We were onsite to repair the canal waste gate's operating mechanism. The shaft was so long and heavy that we had to use two three ton chain falls hung from beam clamps attached to the overhead roof beam.

Celesty adjusting new trash racks at Consolidated Edison's Dwight Station. The rack section was being held out by a 600 volt conduit. Rather then moving the conduit, Celeste picked up the torch and adjusted the racks. That is a 30" wreckers torch she is using. It has been used on many jobs!!

Celeste rigging in the main waterwheel support bearing at the Slater Museum in Pawtucket, R.I.

 

 

Lovell Comstock using his Mack truck with a Peppin backhoe to load the four 33 inch, Hi Test runners onto the trailer.

 

Will determining the best place to set up the crane and how to slice the penstock and draft tubes.

 

Kenny Smith and Celesty adjusting the new racks at Dwight HEP.

Will and Celeste in the ruins of Appleton. Dave and Seth Wright would be dismayed at this destruction.

Celesty taking down the nameplate data at Bristol.

 

Celeste operating the Landoll rig as she carefully pulls the Poreba lathe onto the truck.

Celeste pulling the 35 foot long, 40,000 pound, Poreba roll lathe onto the truck to bring back to the machine shop. Warren Fay (The Wizard), Donny and Will Fay watch.

Will and Celeste dismantling the wet end of Woronoco Hydro's No.2. They have removed the front gate case. They are flanking the exposed main shaft and front runner.

Will and Celeste wonder whether to pull the equipment or rebuild the site!!

Will jacking up the 60 inch Bullard Turret Lathe

A view of the turbine suspended from the chainfalls. All in a days work!

 

60 inch Bullard moved to loading dock by Celeste, Will, Ron, Warren & Bill

Celeste and Mike installing the No.2 unit's shift ring.

Will Fay finishing up the quarter block assembly for turbine two. He is fitting the new bronze screws.

 

FERC ordered us to place an emergency oil spill pan under the transformer at Collins. We needed to get it out to the powerhouse which is set in the river. It was too bulky to drag across the rocks and lift up. I tied a cable to the superstructure, made a loop on the other end and put it on the crane hook. We belted the stainless steel pan to a snatch block. As I lifted up and extended the crane boom, the cable became taunt and the pan was lifted up and it rolled across the chasm to the waiting arms of our riggers. We placed two ten foot, aluminium  I-beams on top of the steel superstructure. We hung four five ton chain falls at the corners of the transformer. We lifted the transformer up, slid the pan underneath and set the transformer down into the pan.

End of a long day! The gang of four!!! Carol, Celesty, Ian, and Will taking a break from sending the transformer pan across the river.

 

Will and Celeste prospecting for "houille blanche". Will!!! watch out for high hazard dams!!!

 

Celesty and Hugh are using the 30 ton porta-power to drive the slip ring collector on to its seat.

Celesty installing a rebuilt Rodney Hunt filler gate. This gate is used to fill the turbine pit prior to lifting the 8 ft high by ten foot wide pit gate. The lifter had two Timken tapered bearings that were rusty. We replaced both bearings, sandblasted and painted the lifter.

Will welding the containment box for the 800 amp circuit breaker to connect the rebuilt No. 2 unit to the main bus bars.

Celeste and Will rigging in the slip ring cover on Pepperell No.2's reconditioned unit.

Celeste, Will and the "Wizard"

Will white blasting the Golden Pond Hydro Kaplan hub. Note blade trunion bearings covered with plywood covers.

 

Celesty and Mike Desroche preparing the camel back hump for Woronoco No. 2. Note the freshly, steel lined pressure case. Note the new pins in the rear gatecase.

Celeste removing the old slate switchgear from Thorndike Lower HEP. Celeste has been operating the crane for years. Lance is taking pictures of me taking pictures!

Celeste rigging the Brockway Mills stator into position. This was really quite difficult. The crane dropped the rotor down 60 feet. Then it had to be pulled side ways beneath the powerhouse floor. Celesty has transferred the load from the crane hook to a 10 ton chain fall attached to an eye bolt fixed to the ceiling.

Celeste and Chris Kruger dropping the Brockway Mills rotor through the hatch in the powerhouse roof. The snow progressed into a blizzard. All in a days work!

Celeste and Chris Kruger close quarter rigging the Brockway Mills rotor into position. This rotor weighs in excess of 14,000 pounds. Watch out Celesty!!!!

Celesty Fay constructing her first dam at Mill Road. She is two years old here!!! Note the giant baloney curl looped over her left shoulder.

 

The Wizard, Kenny Smith and Celesty pulling the 72 inch propellor out of the ESAC unit at Collins. We needed to replace the Ropac mechanical seal that prevents water from leaking into the bulb. The draft tube has been sealed off with the concrete draft gate. We had Mike go down in his scuba gear to seal off the gate before we pumped out the turbine throat. Celesty has put in another long day!!!

The four bladed ESAC runner ready for removal from its throat. Mr. ESAC (Kenny Smith) is the country's leading expert on these units!

 

The catastrophic flood, that injured our dam, also shorted out our generator. Here we are pulling the Hydrolec unit out of the tailrace. We previously unbolted it from the penstock flange. Before this we poured over 100 cubic yards of concrete to stabilize the dam. It has been a very busy, traumatic and trying fall season!!

Here Celesty and Mike Desrouche have pulled the 480 volt conduits off of the 480 volt primaries. They are inspecting the wires for short circuits.

We have raised the turbine up out of the tailrace. We built a temporary scaffold for Will to work on. We had to pump the oil out of the unit. We then removed the porthole on the end of the turbine bulb. This allowed us to disconnect the high voltage wires from the generator leads.

 

 

**************FLASH*********************

September 27th, 2008

    On August 7th, 2008 a microburst hit the intermediate drainage area between Golden Pond Hydro's dam and the main dam at Squam Lake. The flood wave heavily damaged our spillway. It took out the catwalk, flashboards, undermined the spillway apron and shorted out the generator leads. We prepared an emergency, dam, repair permit and applied to the New Hampshire Dam Safety and Wetland's Divisions for their permits. The folks at FERC and the New Hampshire State Agencies responded very quickly. They all worked very hard with us to issue the work permits. We have been working non-stop to repair the dam. We had to first install an access road to access the tailrace and toe of the spillway. Once we had the excavator in place, we cleaned out beneath the apron and formed natural concrete forms out of dry laid stone. We cored three 12 inch diameter cores, 24 inches deep, through the floor of the old apron. We pumped 4.5 cubic yards of concrete beneath the left abutment and then poured another 30 yards beneath the spillway apron. We used vibrators to force the concrete beneath the spillway. Our tailrace training wall had been breached. The wall collapsed into the hole that had been piped beneath it. We formed a new wall on top of the old wall. We pumped another 40 yards beneath the old wall and into the new wall, wooden, forms. We leveled the area in front of the old spillway. We laid 100 pieces of No. 5, 20 foot long, 80 ksi rebar. We drilled the front of the old apron and Hilti glued the rebar into the drilled holes. We poured a new extension of the apron in front of the old one. We have poured 96 cubic yards of concrete as of today. 

Bill Fay waves at the tourist train that had stopped on the old railroad bridge. This is before we poured the new spillway apron extension. You can see the No. 5 rebar mat.

 Please see the attached Picasa album of the destruction and the ongoing repairs.

http://picasaweb.google.com/frenchriverland/GoldenPondDamDamage?authkey=nUCJGifjYLw#

Notes: Please wait for the pages to load. I used high definition j-pegs for all the pictures and documents. When I loaded them into Front Page, I had to shrink them down with the corner cursor. When I shrunk them, they lost resolution!! It seems counterintuitive to me. Anyways, if you want to print any of the materials, download them into a Word document, blow them back up and then print them. You will have excellent results.

 

Will standing on top of the newly installed Hydrolec Turbine. The unit was installed two weeks ago and the paint is already coated with algae! Note how the turbine is bolted to the penstock. Its weight is suspended from the pit walls by four, heavy walled, channel-iron, hanger brackets.

Will is flipping the Hydrolec Unit from, vertical to horizontal, in preparation for lowering it into the abyss. The 18 inch I-beam is cantilevered ten feet off the back wall of the powerhouse. The unit can be rolled, on the trolley, over the tailrace and lowered down to the end of the penstock.

The newly rebuilt, Hydrolec H9H, turbine finally arrives at the Freshwater Hydro Station (aka: Golden Pond Hydro) in Ashland. N.H. Will Fay is attaching the lifting belts and shackles to the crane hook. Lee Nichols of Ashland Electric Light Department is operating the crane. The double drop tractor trailer could not drive down the access road so the unit was moved to this smaller truck. The I-beams and pipe supports for the new installation gantry crane came with the same load.

Will and Celeste rigging the 2000 pound, 18 inch I-beam, for the new gantry, at Freshwater Hydro. Previously, when the unit needed work, George had to hire a 90 ton crane to remove it. After it was repaired, he had the crane back to re-install the unit. Celeste and Will designed the gantry and are now fabricating/installing it.

Will has transferred the load from the three ton chain fall to a 5 ton chain cum-a-long. He removed the chain fall and is lifting the beam closer to the support frame. He has installed a lifting strap around the two beams as a safety. The old railroad bridge is in the background.

 

Celesty is inspecting the No. 2 Unit, at the Lee Pelton Site, in November of 2004. She and Will removed the equipment. They bought the contents of the powerhouse for $ 1000. It was offered to them at the last moment in leau of giving it to the scrappers. It was amazing seeing the two of them, running 30 pound rivet busters, to pry these units out of solid concrete! We still have the three units. Ironically the third unit never ran!. The head losses in the 7000 foot long, 42 inch diameter penstock, with all three units running produced less power than with two units running!!!

 

Slater Museum Hercules Turbine. We have removed the cylinder gate cover. You are looking at the cylinder gate. The flat sectors are where the racks bolted on to the top of the gate. The cylinder is partially withdrawn from the guide vane section. We got four weed eaters powered by barbecue tanks. We heated the cylinder red hot. It expanded the cylinder inside the guide section and crushed the rust that was forming an adhesive band between the cylinder gate and the guide vane section. We were able to slip a very long Sawzall Blade down between the cylinder gate and the guide vane section. We worked the blade around the cylinder circumference and freed it up.

Here we have loaded the cylinder gate cover onto the utility trailer. From left to right, Adrian Paquette, John Remington, Eric Anderson, Will Fay and Mike Desrouche.

We are rebuilding the Holyoke Hercules Turbine at the Slater Mill in Pawtucket, R.I. It will become part of the waterpower exhibit. We are also restoring a very early Jonval Turbine. Here we are removing the rack covers and gate operators. We have since jacked off the bull gear, removed the cylinder cover, removed the cylinder gate and pulled out the runner. This is a very early Hercules. The runner blades are bolted onto the central hub. This makes the runner replacement quite easy. We are having a maple pattern of the bucket made. We will cast new buckets, machine them and bolt them in place. A thin steel band is bolted around the periphery of the buckets to create the skirt ring.

December 7th, 2009. Due excavators fly?? Click below to find out!!!

Flying Excavator <<click here

 December 3rd, 2009      *******FLASH*******

Ken Smith and his sons Ian and Marshall are wrapping up Alternatives Hydro. They are going to go through startup next week. See the Alternatives sidebar for photos from yesterday. It took 8 years from conception to a brand new powerplant!!! Alternatives Hydro <<<click here

September 3rd, 2010, I have been restoring a Niles Boring Mill that can turn a 10 foot diameter object. The work has taken over a year since I purchased the machine from the scrappers. They damaged many pieces and many more pieces had to be replaced because they were worn out. It has consumed all my spare time. Please see the attached Picasa web album that details my efforts:

http://picasaweb.google.com/frenchriverland/NilesBoringMillRebuild#

August 30th, 2010, added Motors as Generators for Microhydro by Nigel Smith.

August 21st, 2010, please see the youtube videos of tests of the Ishida & Service, "Linear Turbine" which Mr. John Service kindly submitted to me from Auckland, New Zealand. I included his e-mail verbatim in the sidebar link:

http://www.youtube.com/watch?v=kggiwGp3A4w
 
http://www.youtube.com/watch?v=ZNrqjMbQ9Ng&feature=channel
 
http://kamomei.blogspot.com/

                                                

          Linear Turbine                                     Test of Linear Turbine      

 

August 19th, 2010, the editor of International Waterpower and Dam Engineering Magazine discovered frenchriverland.com and asked Will and Celeste to write an article on the small scale hydro renaissance that is sweeping the country. Here is a link to the article published in July's issue: Celeste\Water power magazine article July 2010.pdf Enjoy!!!

 

We are very excited! Our Leffel 18Z runner has just arrived from Bob and Ed Shannock's shop. It is a brand new runner and it is beautiful!!

Our crown plate and shift ring were damaged. Ed and Bob made a pattern and cast us new ones. We will have The Wizard machine the rough castings. We need both turbines ready for September 30th for our MTC grant.

Will and I  spent this last weekend with Vern Towers, Bill Munch and John Remington pulling the little 18" Rodney Hunt Type 80 out of Avrill Park, NY. This is a terrible photo. I forgot my camera and had to use my Blackberry. Here we have finally gotten the gate case and runner loose. We are using a wire cum-a-long to pull it out of the remains of the pressure case. We placed a wooden beam from the top of the pressure casing to the top of the remains of the Woodward Governor to use as a lift point.

Will is passing our big wrecking torch to Vern Towers. Here we are removing the elbow halves to access the runner buckets.

Will is reaching beneath the gate case to burn off its mounting bolts

A view of the Avrill Park turbine before we removed it.

This is a classic Fourneyron turbine in the basement of Hal Slotnick's Mill in Holyoke, MA. Note the external vanes are actually the runner vanes. Note the rack and pinion system for opening and closing the cylinder gate.

Two GE, waterwheel driven, synchronous, salient pole, generators going down the road on the same low boy. They are headed from Russell, Ma to dead storage in Athol, MA. There were numerous rubber neckers and double takes along the way!!

Nov 5th, 2009, Moving the Synchronous Hydro Generators to dead storage, click on the following link!!http://picasaweb.google.com/frenchriverland/MovingRussellGeneratorsToDeadStorage#

.

Here is the No. One Generator being loaded onto the ramp truck. They are being trucked to LP Athol to be dry stored. Will & Celesty are installing these units at a new hydrostation they just purchased.

Indian River\Indian_river_Article[1].pdf<<< News Article about our Indian River Plant. Click here!!

October 6th, 2009; Added Smith Bulletin 110

 

September 23, 2009, For a progress report on the 120 inch Niles Boring Mill, please see:

Picasa Web Albums - William - Niles Boring ...

 

******September 2nd, 2009. Added Will's WPI, IQP, Thesis, "Hydrokinetic Energy in Massachusetts".<<<< This paper is going to become a classic!!! This is a really big file. It takes time to load, but it does eventually appear! Please be patient, its worth it!!!****** Hydrokinetic! <<<< Click on this button for Will's thesis!!!!

Will posing between two turbines at Warrensburgh, NY. The left turbine is a 42 inch, Hercules, McCormick turbine made by the Holyoke Machine Company. It is a cylinder gate turbine. Note the large upper cylinder that the internal cylinder gate is raised into. The rectangular covers on the top contain racks that are attached to the top of the cylinder gate. As you rotate the shaft that Will is holding onto, pinion gears mounted on the shaft raise the gate. The right turbine is a 39 inch Samson, Francis Machine manufactured by the James Leffel Company of Springfield, Ohio. This is a crude wicket gate machine.

August 24th, 2009. Added air admission to hydro runners.

August 22, 2009 added stoplog and stoplog structure design.

Researchers were concerned about how slow the site loaded. They said it was because I had too many homepage photos. I removed most photos to the previous pictures file. Now its too big!!!  lol  Well at least you guys can get to the home page now.

 

Please see the attached Picasa album of the destruction and the ongoing repairs at Golden Pond Hydro:

http://picasaweb.google.com/frenchriverland/GoldenPondDamDamage?authkey=nUCJGifjYLw#  <<< click on this link

Celesty in action!!! Here she is making new wicket gate spindles for our Leffell, 33" "B" Turbine. See the pile of spindles on the floor at the lower right.

 

Will operating our flood gate during the freshet of April 9th, 2005. See the photo essay of how we replaced this enormous (8 foot by 10 foot) wooden gate without the aid of a crane:

Please see the attached Picassa album (click on the box below):

 Tannery Gate Rebuild <<<< click on this interactive button

 

 

Old Sturbridge Village Plant

 

Will Fay inspecting High Voltage Conduits

 

This is a photo of my new friend, from Britain, Gazmo. He wrote: "The big circular manifold you can see at the extreme edges were connected by silicon hoses to the stator conductor bars (Where the protective red caps are)and water was pumped through the bars. The whole thing was encased in a substantial explosion proof steel housing which was cooled by the hydrogen. The hydrogen was always at a greater pressure than the water so if a leak happened the water didn't get into the windings. Stator bore was probably about 25ft long on this one. No asbestos . Insulation on most of these machines was Filamic.

The rotor was as impressive .Probably 40+ft long and weighing about 100 ton with maybe an inch clearance either side. Watching the fitters and riggers putting it back without damaging the bore was very interesting. When running this rotor was spinning at 3000RPM.

Edit; Looking at the casing in the pic I think this may have been water cooled only.

This job was a refurbishment and the station closed a couple of years later. I think it ran four of these. The turbine hall was very noisy!"

 

Here is one of our two Leffel runners being loaded on our trailer for transport to Indian River HEP. It is fresh off the Niles boring mill. We had to turn the crown of the runner down to 34 inches to allow it to fit into the S Morgan Smith gatecase. It was really cold with the wind blowing off Cabot Station's canal. Please see:

http://picasaweb.google.com/frenchriverland/DeliveryOfRunnerShaftAndOneRunner#

 

Nov 19th, 2010, Hi everyone, here is a historic moment. After two frustrating years and a $257,000 price tag, Western Massachusetts Electric Company has finally energized our 23,000 volt tie line.

 

Inserting the Indian River crown plate.

 

Here I am sitting in a section of our Indian River's No. One Unit's penstock arriving at the site. Our new substation is on the roof to prevent damage during floods.

 

November 5th, 2010, We are rigging in the crown plate and throat ring of the No. 2 Unit at Indian River HEP. Note the freshly machined, gate seal, surface. We just used the reconditioned 120" Niles Boring Mill to machine these large surfaces smooth. See the following photo from October 3rd when the throat was mounted in the Niles. We should have the rear gate case completely assembled by the end of today!!

November 2nd, 2010, added more captioned photos to the machine shop sidebar illustrating our work. Added some generators forsale to the used equipment section

Will these Leffel runners make it from Chicopee Falls to Turners Falls? Don't worry the tire is only flat on one side!!!

October 30th, 2010 Added "Souvenir Booklet Commemorating the 50th Anniversary of the Opening of the World's First Hydroelectrical Central Station at Appleton, Wiscosin", circa 1932. The Wisconsin Gas and Electric Company Employee Band played the music!

October 23rd, 2010 Added Kingsbury Catalog C-1

October 23rd, 2010 Added C. P. Bradway catalouge

October 22nd, 2010 Added Michell Bearing Catalouge

October 18th, 2010, the Niles Boring Mill is finally operational. See the attached photo of it machining the corrosion from the surface of one of the Indian River HEP's throat/shift ring. We added the custom chip vacuum to prevent chips from falling on the floor. It has taken 15 months to restore this beautiful old machine:

December 3rd, 2010, Here, our No. One generator for Indian River HEP has arrived on site. That is some serious white oak cribbing! We are trying to get all the major components inside our compound before we are buried in snow. The only items left are the new No. One pressure casing and the new No. One draft tube. Yesterday morning it was 15 degrees F and with the wind chill factor it felt like 10 below!!! We had to chop four inches of ice from the forebay floor in order to install one of the 9,000 # Knee braces for the trashrack/fish bypass support structure.

 

Here, Karen is standing in front of the Montana generators shortly after they had been delivered to Leppert Nutmeg to be refurbished. Note how far the stator under hangs the generator base.

 

Here is Celesty in the process of shimming up the Poreba Roll Lathe.

December 24th, 2010 Added a link to photos of us installing the 43" Leffel "F" runners on to the new 18' long by 8" diameter runner shaft that Warren made on the Poreba roll lathe:

Fitting a large runner shaft<<<<< click here

Hey guys! How do you transport a 40 foot long, 10,000 pound, trash rack support beam from the mill yard to the powerhouse over a mountain trail? You use my trustee Ford F-150 and a 16 foot landscaping trailer. It did not do corners very well!!!

 

It scraped the trail in places but I got it over the railroad tracks and around the corners.

"The Wizard" turning one of the 43" Leffel "F" Francis runners in the rebuilt Niles Boring Machine. We finally established an age on this machine tool. It left Hamilton, Ohio on April 17th, 1871. Can you imagine anything coming out of China today being used productively after 139 years. This wonderful, old machine tool has given us the capacity to rapidly rehabilitate our Indian River HEP. With a 10 foot swing, it is one of the few machines of its capacity left in the northeast today!!! I barely saved it from the cast iron maggots!! I adore this machine. After 18 months of rebuilding and $30,000 it is like one of my children!!!! You can see our 900 KW GE/ I.P. Morris T/G set in the background. Peter and Davis were concerned that the metal chips would fly into our generator. At 92 rpm, the chips lazily fall on to the giant chuck!!!! Of course, this machine would be useless without Warren, our "Wizard". Warren spans the world of computer aided machining and hand machines. He can program a CNC planer as easily as running a 139 year old boring mill!! I am so proud of him!!!

Will is making a new governor shaft for the Leffel Turbine. Look at the finish he has produced!!!

Co-conspirators!!! We needed to remove the old wear sleeve from the blade trunion. It was held on by LockTite. In order to remove it, we needed to heat the assembly up to 500 deg F. While Carol was teaching ballet, Celeste and Will snuck the blade into our kitchen. They put the blade in the electric stove and baked it at 500 deg F. I think they may have told Carol that they were baking brownies!!! The high temperature broke the bond and we were able to remove the sleeve.

 

Celesty operating the Milwaukee magnetic base drill. She is installing anchors to fix the rotating field buses to the reconditioned slip rings.

Celesty, Mike and Ian rigging the rebuilt Woronoco No.2 gate case into position. They are re-installing it into the newly grouted pressure casing. Kenny Smith is in the background supervising.

 

 

Our new, American Hydro, replacement runner arriving at Pepperell, MA.

March 5th, 2011, added Miroslav Nechleba

 

The new transition piece that connects our new 8 foot diameter penstock to our new 13 foot diameter pressure casing arrived in four pieces. Here we have welded three of the four quadrants into place. We are using the Galion All Terrain Crane, with its boom extended over the roof of the powerhouse, to set the pieces and tack weld them into place. You can just see the Galion in the far right of the photo. It is sitting on the far side of the tailrace. Note the chain cum-a-longs being used to tug the plate into place. After we finish, we have to reform the back wall around the steel and pour a concrete seal around it..

I thought this photo was interesting. Note the home made jacking screws and chain binders being used to tug and push the joints between the plates into place for final alignment and welding. See the fine lines on the inside of the plate. I thought these pieces were going to be rolled but they were precisely laid out in Auto CAD. They were laid on a press brake. The brake was aligned to each of the lines and the plate was bent 3/8 of a degree on each line. As each line was cumulatively bent, the plate assumed the correct shape.

 

Here, the 20 ton, No. One generator is hanging in mid-air from two 10 ton chain falls just prior to setting it onto its newly poured foundation. You can clearly see how the generator stator under hangs its base and the necessity of the rectangular slot that we provided in the floor. Mike Desrouche, our master rigger is slowly lowering his chainfall. The monorail is slightly off level. The belt in the fore ground is tied to the Galion crane bumper to prevent the generator from rolling.

Here, Ian Smith is guiding the new governor shaft into the powerhouse. Notice the double bell cranks that Warren (The Wizard!) Fay has fabricated from flame cut triangles and pieces of shafting. He has made the keyways in the surface of the shaft extra long. We are installing it now. Once its is in place, we will slide the double bell cranks back and forth until they align perfectly with the shift rings on the Leffel turbine cases. We will then mark the location of the keyways on the double bell cranks. We will remove the bell cranks and bring them back to the shop. We have a beautiful Morrison keyway cutter that will precisely cut the internal keyways into the bores of the double bell cranks.

 

Friday night and I am returning the main shaft to the shop to shorten it by 8 inches. Warren was furious!! He hates to do a job twice. He heated the coupling and cooled the shaft with dry ice. It became a 0.004 interference fit after it reached room temperature. I was going to have it pressed off by the folks at Metso Paper in Chicopee, MA. Warren said he would save me a step. We inserted the shaft into the Poreba lathe yesterday morning. He is turning the 8 inch shaft down on the back side of the coupling, to the bore size of the coupling for a distance of 8 inches. He will extend the keyway for 8 inches using the Bridgeport milling head that he attached to the cross slide of the Poreba Lathe. When he is finished today, I will have Metso press the coupling 8 inches further onto the shaft. We will cut the protruding 8 inches off in the Wells band saw.

 

June 16th, 2011, We are moving the No. One generator into the building and on to its newly poured foundation. Please see the following Picasa web album for details of the process:

https://picasaweb.google.com/frenchriverland/MovingNoOneGeneratorIntoPowerhouse#

No. One generator is being slowly rolled into the powerhouse. We are using pin rollers that are fitted between the generator base and the temporary I-beam frame.

 

June 12th, 2011

Karen in Wappingers Falls HEP posing in front of the Dumont Schneider scroll case turbines. They are operating on 72 feet of head.

Karen posing in front of the Leroy Somers tube turbine at Walkill Station.

Will with Mr. Reitzel inspecting the works at Tannery Pond HEP.

The best part of working on small hydro projects are our beautiful supervisors!!!

Ms. Maura Hennessey posing in front of the newly painted Tannery Pond Unit No. One and Unit No. Two.

 

June 10th, 2011, we have installed the pressure case cover and thrust stand.

Ian Smith and Mike Desrouche are installing the main turbine shaft.

Here, I am flying the No.One turbine thrust shaft over the tarped No.

One generator.

I have extended the crane boom into the powerhouse with the thrust stand hanging from the hook.

 

The thrust stand is ready to be precision aligned to the turbine main shaft. After it is aligned, we will mark the location of the bed bolts. We will drill in with a Hilti hammer drill and glue in four one inch-eight studs.

June 10th, 2011, No. One thrust stand/bearing assembly:

I spent Wednesday sanitizing the thrust bearing and housing. I used the 15 ton Galion crane to place the shaft on the floor in front of the garage door. I lifted the thrust stand up and rolled the shaft beneath the thrust stand. I then lowered the stand back to the floor. I had to do this because I could not extend the crane boom past the thrust stand with the shaft hanging from it. The overhead monorail does not extend to the garage door.

Here, I am lifting the shaft with a 2 ton chain cum-a-long. The scrappers in Montana cut the thrust shafts off of the turbine casings. This shaft had enough left on the cut side to fit a new coupling to. We had previously purchased all the 8 inch shafting and couplings from the mill building where our machine shop is. The shafting used to be driven by an enormous Corliss steam engine. Warren fitted one of the Corliss half couplings to the other end of this shaft.

This naval brass ring is a slinger ring. It's purpose is to lubricate the shaft journal. In essence, it is a primitive lubrication pump.

Assembling the bearing with STP.

Here, I have inserted the shaft into the lower babbitt bearing shell. I have poured STP onto the bearing before I set the shaft down into it. I poured more STP onto the shaft journal. Notice the cylindrical stepped lobes that are machined onto the surface of the shaft. These fit into grooves in the babbitted bearing shell. When the shaft is pushed in an axial direction, from either end, the sides of the lobes push against the walls of the slots and take the axial force. The three bronze rings are called slinger rings. They dip into the pool of oil in the lower housing. As the shaft revolves, the slinger rings are slowly dragged around. The oil sticking to the rings falls off onto the shaft and lubricates them.

Here is the fully assembled thrust stand ready to be moved into the No. One power room. I had to support the far end of the shaft because it protrudes more out the generator end then the turbine shaft's end.

October 11th, 2011, added "Water Turbines; Contributions To Their Study, Computation And Design" by Professor S. J. Zowski. This is a great paper by one of the leading turbine designers of his time. Zowski invented the high speed runner with his "Free Whirl Zone". These runners included the Morgan Smith "S", the Rodney Hunt Type "105", and the Leffel "Z" and Leffel "S" runners. They were characterized by a bell shape where the crown of the runner was approximately 1/2 the diameter of the skirt ring. The specific speed in English Units varied from 100 to 105.

October 11th, 2011, added design notes and powerhouse reinforced concrete calculations for the Natick Dam HEP.

August 21st, 2011,  we finally got the second unit into commercial operation. We are finalizing the downstream fish passages and doing cosmetic duties.

Karen, Cleo and Tut in front of the finished No.One Unit's salient pole generator.

Karen and Tut in front of the new No. One pressure casing. Note the thrust stand, new couplings and disc brake rotor behind her. Note the new Sorenson hydraulic power pack. The blue cylinder is a hydraulic accumulator 1/2 filled with nitrogen gas and 1/2 filled with pressurized oil. In the event of an emergency shutdown the gas pushes the oil through an electric dump valve and forces the hydraulic cylinder to close the turbine. The dump valve is closed by electricity. If the power fails it opens up to close the unit down.

Karen and Cleo in front of the running No. Two unit. Notice the brown primer on the side of the pressure tank. We are starting our final painting process. We love the baby blue brightwork!

July 27th, 2011, added, "The Hydraucone Regainer, Its Development and Application In Hydroelectric Plants", aka: White Hydraucone. This is one of the most venal exchanges, between the two foremost hydraulic engineers of the last century, that ever played out in the Transactions of the Society of Mechanical Engineers!!!

The up shot of all the brouhaha is that curiously, both designs worked exceedingly well!! They were also very expensive. White's theory was that the easiest way to turn a jet was to impinge it on a flat plate. Moody thought that was ludicrous and you would lose tremendous amounts of energy. Moody thought you could eliminate rotational core losses by having the solid uprising cone preventing anti rotational vortices. White thought that was ludicrous and the secondary uprising cone would produce huge friction losses. So it was an unpleasant surprise to both of them, when TVA model tested and installed both prototype draft tubes, and got recovery efficiencies greater then 94 %.

Maura Hennessey and Will Fay removing stop logs in the forebay at Tannery Pond. The waterbox had been empty for two years while Will replaced the trash racks and installed Units Two and Three. When Davis and I installed this 36 inch main carrying beam, and the vertical stop log channels, back in 1994, we installed them in front of the trash racks. This allows the racks to be replaced without draining Tannery Pond. Will and Maura started rock climbing last year. They have become quite strong!! It makes it easy to work the chain cum-a-long to pull the stop log panels.

Hi everybody, Will has energized Tannery Pond Unit Two for the first time! Here I have caught the drama of him throwing the breaker in!! Congratulations Will!!!!! It has been a long, productive and educational road!!

Will is determining the speed of Unit Two to allow for a soft start. The digital tachometer was not wired up yet so he used my father's Biddle tachometer. He had to catch the center of the spinning I- bolt.

The supervisor girls are ecstatic!!!!

June 21st, 2011, on Thursday and Friday we lowered the No. One generator onto its new pedestal. I trucked the new governor shaft to the site. Yesterday, Industrial steel and Boiler arrived with the new eccentric, off set cone that connects the new 8 foot diameter penstock to the new 13' diameter pressure casing. It came in 4 pieces so that two men could assemble it. Cole used the little Galion all terrain crane to swing the pieces into place. Our pedestal was too close to the pressure casing by 8 inches. Warren is turning the 8 inch main shaft to adjust its length. Here is a new Picasa Web album:

https://picasaweb.google.com/frenchriverland/MovingNumberOneGeneratorIntoPowerhouseII#

Will Fay and beautiful Maura Hennessey in front of the newly finished No. 3 Unit at Tannery Pond. It is so difficult to wash Never-Seize from your hands!!!!

Karen Westerman and Marshall Smith gaze in wonder at the newly installed switchgear at Tannery Pond HEP. Note the elaborate, large port, valve stack Marshall and Will installed on the Woodward Governor. They previously removed the flyball head to be able to install the four way valve. The valve is actuated by electric solenoids. The solenoids will be controlled by the Allen Bradley, SLC 500, programable logic controller.

The newly completed No. Two unit at Tannery Pond HEP. Note all the details. Will Fay has designed, Auto Caded, machined, rigged in and installed the Main shaft, main shaft  1/2 couplings, shift arm turn buckle arms, governor shaft, governor shaft foot bearing, lignum vitae quarter blocks, nose bolts, eccentric pins, wicket gate pins, finished wicket gates, tie rod ends, tie rod bolts and wicket gate links. He has become and outstanding civil and mechanical engineer, machinist, business man and entrepreneur!!!!

Will and I posing for Karen in front of the No. 2 Unit at Tannery Pond HEP.

April 25th, 2011, here, Marshall Smith of Smith Alternative Energy (www.smithtest.com) proudly poses in front of the newly installed switchgear for Tannery Pond HEP, on the Millers River, in Winchendon, MA. In the background is the newly installed generator control center. Marshall, his father, Ken Smith P.E. and his brother Ian Smith have designed and installed the electrical controls. It has been a trying process as they have also concurrently been designing and installing the control system for our Indian River HEP on the Westfield River, in Russell, MA. Three Allen Bradley SLC 500 PLCs automatically control the three TG sets. A continuous record of headwater, tailwater and bypass reach water levels is made for FERC verification.

Here, Karen is inspecting the three TG sets at Tannery Pond HEP. Notice the main thrust bearing support plate recently installed beneath the No. 2 Unit.

Will and Celesty are removing the flywheel from Woronoco No. Two. In this photo, Will is 13 and Celesty is 15.

Here, Karen is painting the crown cover of one of the two Leffel 43" Type "F" camelback turbines that will be installed as the No.One Unit at Indian River HEP. I previously chased the threaded holes, de-scaled the surfaces and wire wheeled the surfaces. Karen is a great sport and the only SRHOCO spouse who has ever done any physical work on our powerplants!

February 21st, 2011, added Byron McCoy's 1952 paper on the "Evolution of Hydraulic Prime Movers". Mr. McCoy was a water power engineer for Charles T Main Company of Boston, Massachusetts during the 1950s and 1960s. Please enjoy it: Byron McCoy<<< click here!!

My good friend, Ian Smith, posing in front of the Hillsborough, N.H., Henry Obermeyer, chain drive turbine. His father, Ken Smith, his brother Marshall Smith and he formed Smith Alternative Energy in 2009. They have completed many interesting hydro projects in the interim. Please see their site: www.smithtest.com <<< click here to peruse their photo albums. Please call them at 413-427-4236 or 508-867-6976 for any hydro related work.

Here, you see the top cover of the famous, Henry Obermeyer, chain drive turbine removed. Note the silent chain looped over the upper, output shaft. Henry is a prolific inventor/designer. He is now manufacturing a unique Bascule Gate that has been installed worldwide. See his unique gate system at:

http://www.obermeyerhydro.com  or call him at 970-568-9844

January 30th, 2011 Revised draft tube web page. Added photos of draft tube construction and installation.

Rigging a large generator  <<<<<< click here

Fitting a large runner shaft <<<<< click here